The biggest ever modular build construction project in the UK

23rd November, 2016

Premier Modular, the East Yorkshire-based manufacturer and constructor of modular buildings, has been appointment to provide a series of modular building complexes at Hinkley Point C in Somerset following EDF Energy’s Final Investment Decision.

The complex will deliver offices and site welfare facilities required for the construction phase of the new nuclear power station.

The 38,000m² of office space – the largest modular project awarded in the UK – will house all the management and technical personnel required during the construction stage of this much needed new nuclear power plant. Almost 1000 steel framed modules are being constructed off site, before being transported to site for final assembly and fitting out – a process that will take only 16 months from manufacture to hand over.

Original link PSBJ


Share this content

 


Comments

Enter your name and your comment below. Your e-mail address will not be published on the website.