In creating the UK’s tallest build-for-rent development – Highpoint in London’s Elephant and Castle – flexibility, efficiency and speed were key concepts for contractor Mace and structural engineer AKT II.
Like any residential scheme the cost principles of optimising the lettable area, getting the number and right mix of apartments remain true for private rented sector (PRS) – only more so. Design-and-build contractor Mace and its structural engineer AKT II have worked hard to develop an efficient design to maximise lettable area and optimise flexibility of the floor plates. The team has also developed an innovative structural solution and standardised as much as possible to improve efficiency, speed up construction and minimise costs. “This scheme was about starting with a blank sheet of paper and saying ‘how can we design one of the tallest residential towers in the capital to be built quickly, efficiently and leanly’,” says Rob Partridge, a director at AKT II.
Surprisingly, the design concept dates back 13 years to 2004, when AKT II first worked on the scheme with architect Rogers Stirk Harbour + Partners for developer First Base, with backing from government regeneration agency English Partnerships. Together architect and engineer set out to design a residential tower with apartments for sale and rent that would be quick and efficient to build, with open floor plates to allow the developer flexibility on how they were configured. It is a testimony to the robustness of the solution developed then that it is still the best solution for PRS over a decade later.
Compact
The site defined the building’s compact footprint, so the design team set out to make its concrete core as small as possible in order to maximise lettable space on the floor plates. A solution was developed with a core measuring just 10m x 10m, big enough to accommodate the building’s four lifts, a staircase and the service risers but little else.
To build stiffness into the tower Partridge added a rigid perimeter structure with the addition of prefabricated reinforced concrete panels to the perimeter of the 26m x 26m floorplates. Two panels are incorporated into the facade on each elevation.
In the super-slender towers of New York and Chicago the core is tied to the perimeter every 12 floors or so by giant beams, to create a single stiff structure. “Instead of just the core taking lateral loads, by mobilising the perimeter structure the whole volume of the tower works to provide stability,” explains Partridge. The downside of this solution is that the outrigger beams are so large that the floors on which they are located are generally only suitable for use as plant rooms.
Rather than lose valuable lettable space, for Highpoint AKT II’s innovative structural solution has been to split the giant beams into thin horizontal slices by designing each of the tower’s 250mm-thick reinforced concrete floor plates to act as a mini-outrigger. The floors link the core to the precast concrete perimeter panels.
Additional lateral stiffness is provided by the tower’s internal structure of four diagonal reinforced concrete walls. These buttress the central core, but are separated from it by the circulation corridor that rings the core. The walls are positioned on a line from the corner of the tower’s core to the furthermost corner of the tower’s corner balconies, a positioning that ensures they are integrated into the diagonal separating walls between apartments.
“We used walls, as opposed to columns, to reduce the number of components internally because you need fewer of them and the walls also provide additional lateral stiffness,” explains Partridge.
Carefully detailed reinforcement design ensures that both the diagonal walls and the perimeter walls are tied into the floor slabs to create a homogeneous structure. “The reason the structure is so lean is that every concrete element, and the joints between them, all work as part of the stability system in addition to resisting the vertical loads,” Partridge says.
The structural design was then further rationalised to enable all vertical structural components to be standardised so that they can be prefabricated in order to simplify construction and reduce build time. “We had to go outside the codes because design guidance for precast walls has a limit of 12 storeys and this building has 47,” says Partridge.
The reinforced concrete facade panels are prefabricated as a single element. The diagonal wall panels are prefabricated using a twin-wall system. Twin wall enables reinforcement to be inserted between the two biscuits of concrete that form the front and back faces of the wall, after which concrete is poured the void to create a solid unit. “We designed a solution where all components are the same dimensions, whichever floor they are on; the only difference being the amount of reinforcement they contain,” says Partridge.
Efficient
The original scheme was granted planning permission but was put on hold when the recession hit in 2008. In 2010, English Partnerships (now renamed Homes and Communities Agency) resurrected the scheme. Mace Developments submitted the winning tender with its PRS scheme funded by Realstar. Mace Construction was subsequently appointed to build the scheme under a fixed price design-and-build contract, retaining AKT II as structural engineer and employing Axis Architects as its delivery partner. Enabling works started in November 2014. In January 2015, construction commenced.
This is only the second time this particular platform had been used in the UK. Its advantage is that it has in-built hydraulic jacks to raise the rig without the need of a crane, which means it can operate in wind speeds of up to 72km/hour. The rig is on two levels: the tower cranes deliver materials, including the core’s precast concrete stairs, to the top level from where they are fed through hatches to the workers safely enclosed on the level below. “The rig allowed us to store enough rebar on top level to construct two floors in advance of those times when high winds limited crane use,” explains Bart Lemmens, Mace senior project manager.
The core was constructed at a rate of one floor every six days. Following four floors behind, and hidden from view behind a second Doka climbing screen, were the floor-laying team. Their role was to cast the concrete floor slabs on top of the precast concrete perimeter panels and the diagonal twin wall elements. “The driver for the use of precast was to save time, it knocked about a day per floor off the programme,” says Guy Hunt, Mace project director. “On average we were completing one floor every six days – it would have taken nine days per floor using conventional construction,” he adds.
As soon as the climbing screen clears a floor the building’s four external hoists are extended upwards to connect to the new floor so that fit-out can commence. First onto the empty floor plates are the prefabricated bathroom pods and prefabricated service cupboards. Again, the design has been rationalised so that there are only three models of bathroom pod: a right-hand model, a left-hand model and an en-suite model. As soon as the pods have been wheeled into position, the cladding team moves in.
Cladding contractor Yuanda was responsible for installation of the facades and for the giant yellow triangular steel balconies. The balconies have been designed to be self-supporting so that they can be installed without the need for temporary props on site, simplifying construction. However, from the edge of the floorplate to the tip of the balcony is a 4m cantilever, the length of which means that without some form of restraint the balconies would be very springy indeed. AKT II’s solution is to link the tips of the balconies together vertically using Macalloy rods and then to tether the Macalloy rod to one of the arms of the building’s structural crown to help damp any movement (see below).
Once the weather protection was in place, the fit-out teams then began their race up the tower. There are 44 floors of eight apartments to fit out. To ensure fit-out went smoothly, Mace had a trial apartment built off site to iron out any snags before the race commenced. “Repetition is a big part of the success of this job; every floor, from floor 2 to 44 is the same,” says Hunt.